Updates: June 19, 2017

Following is a summary list of construction activities that took place last week at the building as management continues to repair and rebuild the A-L line to the highest standard so residents can return home as quickly as possible.

  • Parapet demolition has been completed on the north and east walls of the A-L line; re-build of the parapet will begin next week
  • Interior demolition of the 5th Floor is completed
  • Interior demolition of Floors  1 & 2 is about 80% completed
  • Content removal of Floors 3 & 4 remains underway