Updates: July 10, 2017

Following is a summary list of construction activities that took place at the building prior to and following the July 4th holiday, as management continues to repair and rebuild the A-L line to the highest standard so residents can return home as quickly as possible.

On the A-L line of the building

  • Removal of pipe risers continue on the 5th and 6th Floors
  • Installation of temporary roof on the 5th Floor has begun
  • Removal of the 6th Floor parapet is 60% complete
  • Abatement of kitchen floors on the 5th Floor is scheduled to be completed this week
  • Pressure testing and gas riser work has been completed, with DOB inspections to follow
  • Interior demolition of the 3rd and 4th Floors remains underway

On the M-U line of the building

  • Elevator repairs continue, with completion anticipated next week
  • New temporary flooring on the 6th Floor hallway is installed
  • Coating and painting of the 6th Floor hallway is almost completed
  • Re-occupancy of the 6th Floor is now scheduled for the week of July 17, following DOB inspections