Following is a summary list of construction activities that took place at the building last week, as management continues to repair and rebuild the A-L line to the highest standard so residents can return home as quickly as possible.

On the A-L Line of the building

  • Interior abatement on the 5th and 6th Floors is completed
  • Architectural drawings are 80% completed
  • Repair on the roof and parapets are ongoing

On the M-U Line of the building

  • Elevator repairs are completed and service is restored
  • The 6th Floor vacate order has been lifted
  • Gas risers have been tested and restored throughout the M – S Lines, along with the following apartments: 2P, 3P, 5P, 6P, 1R, 2R, 3R, 4R, 6R, LT, 2T, 3T, 5T, 6T, 1U, 2U, 3U, 6U; management is awaiting access to the remaining apartments on this line