Updates: July 25, 2017

Following is a summary list of construction activities that took place at the building last week, as management continues to repair and rebuild the A-L line to the highest standard so residents can return home as quickly as possible. 

  • Demolition of interior walls is 100% completed on the 5th Floor, 90% complete on Floors 1-4, and 10% complete on the 6th Floor
  • Interior abatement of the 4th Floor is 90% complete, with abatement work also underway on the 3rd Floor
  • Installation of a water-tight temporary roof on the 5th Floor is 95% complete