Updates: August 31, 2017

The following is a summary of recent construction activities taking place in the building as management continues to repair and rebuild the A-L lines so residents can return home as quickly as possible:

  • Equipment for the new elevator has been ordered
  • Horizontal members that provide structural support for the roof (“joists”) are being replaced and abated
  • Parapets are being rebuilt in tandem with joist replacement
  • All interior abatement on the Ground Floor through the 6th Floor is 100% completed
  • Demolition of the interior concrete masonry shafts is completed on Floors 1 – 4
  • All interior renovation plans have been submitted and are pending DOB approval